Building & Electrical - Commercial Fees
C. Resolution #09-308, Effective 04/01/2009

Click on the questions to view the answers.

Building Permit:

See Graduated Fee Schedule-Click Here

Electrical Permit:

$200.00 plus $2.50/100 sq. ft. (plus 3% State Surcharge)

Industrialized Units/Construction Trailers:

$200.00 Plus $1.30 per 100 square feet (plus 3% state surcharge)

HVAC:

$200.00 plus $2.50 per 100 sq. ft. (plus 3% state surcharge)

HVAC Replacements:

$200.00 plus $50.00 each unit (plus 3% state surcharge)

Public/Commercial Swimming Pools:

$400.00 (plus 3% State Surcharge)

Tents:

WARREN COUNTY - $200.00 (plus 3% State Surcharge)


CITY OF LEBANON - $75.00 (plus 3% State Surcharge)

Fire Alarms/Hoods/Suppression/Sprinklers:

$400.00 (plus 3% State Surcharge)

Retaining/Entry Walls:

$200.00 (plus 3% State Surcharge)

Bridges/Fountains:

$200.00 (plus 3% State Surcharge)

Security Systems:

$200.00 (plus 3% State Surcharge)

Signs/Awnings:

$200.00 (plus 3% State Surcharge)

Solar Collector/Wind Turbins:

$400.00 (plus 3% State Surcharge)

Water Towers:

$400.00 (plus 3% State Surcharge)

Cellular Towers/Dishes:

$400.00 (plus 3% State Surcharge)

Sales Trailer:

$400.00 (plus 3% State Surcharge)

Fire Damage/Demolition:

$200.00 (plus 3% State Surcharge)

Plan Revision:

$200.00 (additional plan revision correction letter will be $200.00 each. First three are included in price of permit)

Lost Set:

$200.00

Extra Inspection Fee Of Failed Inspection Fee:

$200.00
Requested before or after hours $150 per hour per inspector (must be paid in advance)

Cancelled Permits/Re-active Permit:

1/2 off original fee (not to exceed $200.00. Permit will be cancelled if not picked up in one year or is dormant for one year.)